§PIProject Intelligence & Digital Construction

Project information in service of execution.

We use data and digital tools to plan, measure and control projects, and to give clients a clear view of site status.

Illustrative image

  • PI-01

    Project Planning

    Activity-based schedules with milestones, dependencies and critical path.

  • PI-02

    Progress Monitoring

    Physical progress measured by work front and compared with plan.

  • PI-03

    Cost Control

    Budget, commitments, incurred cost and forecast final cost.

  • PI-04

    Risk Management

    Risk register with owners, likelihood, impact and actions.

  • PI-05

    Document Control

    Revisions, transmittals and approvals with traceability.

  • PI-06

    Information Governance

    Rules for numbering, access and retention of project information.

  • PI-07

    BIM and digital coordination

    Models and digital coordination of disciplines, where applicable.

  • PI-08

    Reporting & Dashboards

    Periodic reports and dashboards with the KPIs agreed with the client.

§PI.2Demo

Demo dashboard

Simulated data for demonstration. It does not represent a real project or Ekton Construction results.

LILET_Executive_Dashboard · Ekton Project IntelligenceDEMO · ILLUSTRATIVE DATA
L

Lobito Industrial Logistics & Deepwater Marine Terminal [LILET]

Lobito, Angola | ISBL — Marine & Berthing EPC | OSBL — Rail & Bulk Logistics EPC | Data as of May 2026

Physical Progress

46.4%

▼ 3.6% vs plan

0%100%

CPI

0.98

Over budget

0.51.5

SPI

0.93

Behind schedule

0.51.5

TCPI

1.02

Required to complete within approved budget

Safety – LTIR

0.08

▼ -0.02 · per 200k hrs

01

Open Punch Items

138

ISBL 72 | OSBL 66

0300

Forecast COD

Q4 2026

Current forecast

EV $195M|AC $199M|PV $210M|CV -$4M|SV -$15M|EAC $428M|BAC $420M

Physical Progress S-Curve

PlannedActualForecast
0%25%50%75%100%Behind plan by 3.6%46%100%100%Jan '25Mar '25May '25Jul '25Sep '25Nov '25Jan '26Mar '26May '26Jul '26Sep '26Nov '26Monthly

Cumulative Cost – USD Million

Planned BudgetActual CostEAC Forecast
0M125M250M375M500MAC $199M199M420M428MJan '25Mar '25May '25Jul '25Sep '25Nov '25Jan '26Mar '26May '26Jul '26Sep '26Nov '26Monthly

Top 5 Variances by Unit

UnitVariance TypePlannedActualVarianceStatus
SHIPLDScheduleBaselineCurrent+42 daysCritical
RAILLPScheduleBaselineCurrent+42 daysCritical
BERTH1ScheduleBaselineCurrent+25 daysHigh
SUBSTNScheduleBaselineCurrent+25 daysHigh
FUELTKScheduleBaselineCurrent+17 daysHigh

MC Progress by System Type

Mechanical Completion · Check Sheet A
Marine
MAR / CIV / STR
43%
Bulk Handling
MEC / ELE / INS
45%
Rail
CIV / MEC / TEL
47%
Power
ELE / INS
47%
Utility
PIP / MEC / ELE
46%
Buildings
CIV / STR / ELE
71%

Primary disciplines responsible for Check Sheet A – Mechanical Completion.

Unit & System Register – Execution Control View

Unit CodeUnit NameType of SystemKey SystemsConst. Resp.Comm. Resp.Cross-boundaryProgress %MC Discipline
BERTH1Deepwater Berth 1MarinePiled quay / Fenders / BollardsMarine EPCMarine EPCNo
46%
MARCIVSTR
BERTH2Bulk Berth 2MarineQuay deck / Mooring / Dredged pocketMarine EPCMarine EPCNo
38%
MARCIV
SHIPLDShiploader SystemBulk HandlingTravelling shiploader / Rails / Cable reelMarine EPCMarine EPCYes
31%
MECELEINS
CONVEYJetty Conveyor GalleryBulk HandlingBelt conveyors / Transfer towers / DustMarine EPCMarine EPCYes
44%
STRMECELE
SILOSBulk Storage SilosBulk HandlingSilos / Reclaim / WeighbridgeLogistics EPCLogistics EPCYes
57%
CIVSTRMEC
RAILLPRail Loop & Car DumperRailTrack / Car dumper / SignallingLogistics EPCLogistics EPCYes
39%
CIVMECTEL
RAILYDRail Marshalling YardRailSidings / Turnouts / LightingLogistics EPCLogistics EPCNo
62%
CIVELE
SUBSTN60 kV Main SubstationPowerHV / MV / Transformers / UPSLogistics EPCLogistics EPCYes
52%
ELEINS
SHOREPShore Power & LightingPowerMV feeders / High-mast lightingMarine EPCMarine EPCYes
35%
ELE
DESALDesalination & Industrial WaterUtilityRO / Storage tanks / DistributionLogistics EPCLogistics EPCNo
68%
PIPMECELE
FUELTKFuel & Bunkering Tank FarmUtilityTanks / Bunker lines / Fire waterLogistics EPCLogistics EPCYes
41%
PIPMECINS
SCADATerminal Control & SCADAUtilityTOS / SCADA / CCTV / FibreLogistics EPCJointYes
29%
INSTEL
ADMINAdmin, Workshops & GateBuildingsOffices / Workshop / Gate complexLogistics EPCLogistics EPCNo
71%
CIVSTRELE

Critical Interfaces – Marine ↔ Onshore

InterfaceFromToOwnerStatus
Jetty conveyor tie-inCONVEYSILOSLogistics EPCIn progress
Shore power 11 kVSUBSTNSHOREPLogistics EPCOn track
Shiploader railsBERTH1SHIPLDMarine EPCCritical
Car dumper feedRAILLPSILOSJointIn progress
SCADA / TOS integrationSCADAAll ISBLJointDefining

Top 5 Risks & Mitigation

RiskProb./ImpactOwnerMitigationTrend
Marine pile refusal at Berth 1H/HMarine EPCPile driveability review
Shiploader delivery slippageM/HMarine EPCExpedite FAT & shipping
Dredging window conflictM/MMarine EPCResequence dredge plan
Rail signalling acceptanceM/HLogistics EPCEarly SAT with operator
60 kV grid connection dateL/HLogistics EPCTemporary generation plan

Open Punch Items & Actions – Next 30 Days

ActionResponsibleDueStatus
Close shiploader rail survey NCRMarine EPC12 JunIn progress
Submit dredge spoil permitMarine EPC30 MayOverdue
FAT – car dumper drivesLogistics EPC10 JunOn track
Energise MV switchboardLogistics EPC05 JunCompleted
Freeze SCADA I/O listJoint25 JunNot started

Total open punch items: 138 | ISBL: 72 | OSBL: 66

Data refresh: weekly | Last refresh: 28 May 2026 08:00 | Fictional demonstration project — not an Ekton Construction project or forecast